THANKS to modern engineering, a bridge has been erected across both carriageways of the busy N3 at Hammarsdale in just four days.

Traffic on the main arterial between Durban and Pietermaritzburg was diverted for two consecutive weekends to make it possible for the project.

The development of the Keystone Park Light Industrial, Warehousing and Logistics Precinct at Hammarsdale has increased the volume of traffic – especially heavy vehicles – using the intersection of the N3 and MR 385.

Loadtech

The South African National Roads Agency (SANRAL) decided that the interchange must be upgraded from a simple diamond interchange, to a new semi-parclo (partial clover leaf) free flow interchange to prevent a back-up of trucks onto the N3.

SANRAL Eastern Region project manager Stephné Wilmot said given the high volumes of traffic using the N3 and the urgent need to construct the intersection as soon as possible to alleviate growing congestion by heavy vehicles, it was decided to use time-saving construction measures.

Ian Jackson, resident engineer at Hatch consulting engineers, said in order to minimise delays, precast beams were used.

“With short to medium span bridges, you basically have three types of decks – cast in-situ; precast beams and deck slab; and a launched deck.

“The cast in-situ is the cheapest but will entail closing a carriageway for approximately three to four months and diverting both directions of traffic onto the one carriageway and then repeating the procedure for the next deck. Thus, it is time consuming and severely affects traffic.

“A launch deck is cost prohibitive because it is expensive to set up the launch yard. The geometrics of the bridge would only allow the launch of two decks. Thus, there are practical and cost constraints.

“Thus, a precast beam deck and slab has the least disruption of the traffic – two days in which to place the beams across each carriageway – and is also the most cost effective.”

Jackson said the beams were cast in a specialised casting yard approximately five kilometres away from the construction site.

The beams were transported from the casting yard to site with special low-bed vehicles.

As each beam weights 37 tons, a large substantial crane was used to lift and place each beam in position.

It took two days to position 23 beams per deck. Owing to the positioning of the crane to lift the beams and the potential danger to traffic, each carriageway was closed during the lifting and placing operation.